Experience

Project Info:
Owner:
City of Bangor, Maine

Technologies/Materials:
Pump Station Butterfly Valve Replacement

Architect:
AECOM

Engineer:
City of Bangor - Engineer

Project Value:
$117,800

Project Highlights:
The work had to be completed during dry weather and off peak hours, with normal treatment plant operations uninterrupted.


Download Project PDF

Bangor Butterfly Valve Removal and Replacement - Bangor, ME

This project involved the removable and replacement of an aging Butterfly Valve at the Kenduskeag Pump Station (KPS) at the Wastewater Treatment Plant (WWTP) in Bangor, Maine. Additionally, Methuen Industrial Services replaced existing electrical work and wiring, plus the testing of all equipment and electrical components.  This was a critical project for Bangor since the Kenduskeag Pump Station takes wastewater from approximately 2/3 of the City. 

How Can We Help?

Tell us about your project and we'll provide you with a custom solution to fit your needs and budget.

Maybe later.
How can we help?