Experience

Project Info:
Owner:
City of Fitchburg, MA

Technologies/Materials:
Aerated Grit Removal System

Engineer:
Wright-Pierce

Project Value:
$7.4 Million

Project Highlights:
The new facility will handle gravity fed flows up to 50 Million Gallons per Day (MGD)


Download Project PDF

Fitchburg Aerated Grit Removal System - Fitchburg, MA

Methuen Construction was the General Contractor for the installation of an aerated grit removal system at the Fitchburg, MA East Wastewater Treatment Plant., The new facility will handle gravity fed flows up to 50 million gallons per day. As the General Contractor for the upgrade and expansion, Methuen Construction was required to temporarily relocate all daily processing functions to be able to build the new structure with no disruptions to existing operations. This effort was accomplished without flaw and allowed the site and concrete work, self-performed by Methuen Construction, to begin.

How Can We Help?

Tell us about your project and we'll provide you with a custom solution to fit your needs and budget.

Maybe later.
How can we help?